  • FIDIC New Red Book – Can be used in any kind of Engineering Construction Contract
  • FIDIC New Yellow Book – Applies to the “lump sum contract project” where the Contractor takes participation in the design work.
  • FIDIC Silver Book – Applies to the “turnkey projects of infrastructure or large-scale factories” where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period.
  • FIDIC Green Book – Can be used in all kinds of small-scale projects.

Altogether these four Contract Conditions can be applied to nearly every kind of project, except for that of managing contracting or simply consulting or designing.

Reference: Anil Yadav, Ashok Pershad, Dhiraj Gaur Manoj and Mukul Verma

 

Hakkında Cumhur Şamiloğlu
Civil Eng., MRICS Management of International Business (MSc-2002)

Bir Cevap Yazın

Aşağıya bilgilerinizi girin veya oturum açmak için bir simgeye tıklayın:

WordPress.com Logosu

WordPress.com hesabınızı kullanarak yorum yapıyorsunuz. Log Out / Değiştir )

Twitter resmi

Twitter hesabınızı kullanarak yorum yapıyorsunuz. Log Out / Değiştir )

Facebook fotoğrafı

Facebook hesabınızı kullanarak yorum yapıyorsunuz. Log Out / Değiştir )

Google+ fotoğrafı

Google+ hesabınızı kullanarak yorum yapıyorsunuz. Log Out / Değiştir )

Connecting to %s

%d blogcu bunu beğendi: