Is contractor entitled for variation in lumpsum contracts?

Yes. Lump sum contract means the contractor has to execute the works for a specified amount fixed in the contract. In a lump sum contract, the contractor is bound to execute works for the completion of the project as detailed in the contract documents; in some cases a bill of quantities will also be included. In either case if a specific work is not detailed in the contract or if alterations are required, then it can be treated as a variation.
Examples of variation in lump sum contracts
 
An example of variation in lump sum contract is removal of a building or structure which is not described anywhere in drawings or contract documents. Another example is alteration to the details mentioned such as replacing painting works with tiling. A variation order is required to be obtained from the owner/ Engineer before executing the works.
Thanks to http://civilengineeringarticles.blogspot.com
Reklamlar

Hakkında Cumhur Şamiloğlu
Civil Eng., MRICS Management of International Business (MSc-2002)

2 Responses to Is contractor entitled for variation in lumpsum contracts?

  1. Harika eş site okunuşu çok memnunuz sizden. Her
    madde kusursuz görünüyor. filvaki sitenizi kovuşturulma ediyorum.

Bir Cevap Yazın

Aşağıya bilgilerinizi girin veya oturum açmak için bir simgeye tıklayın:

WordPress.com Logosu

WordPress.com hesabınızı kullanarak yorum yapıyorsunuz. Çıkış  Yap /  Değiştir )

Google fotoğrafı

Google hesabınızı kullanarak yorum yapıyorsunuz. Çıkış  Yap /  Değiştir )

Twitter resmi

Twitter hesabınızı kullanarak yorum yapıyorsunuz. Çıkış  Yap /  Değiştir )

Facebook fotoğrafı

Facebook hesabınızı kullanarak yorum yapıyorsunuz. Çıkış  Yap /  Değiştir )

Connecting to %s

%d blogcu bunu beğendi: